Title:
|
Historic Courthouse Change Order Authorization
Staff recommends approval to allow the Procurement Director to execute necessary amendments to the existing Chasse Building Team Contract No. CT-FM-19-347 to complete the site work around the Historic Courthouse, provided the multiple amendments for the additional defined scope of work does not exceed $900,000.00 and the expiration date does not exceed December 31, 2020.
|