Title:
|
Award: Contract No. PO2500004343, Hunter Contracting Co. (Headquarters: Gilbert, AZ) to provide Pre-Construction Services for Construction Manager at Risk (CMAR) services: Canoa Ranch Sewer Extension (3CRAEX). This award of contract is recommended to the highest qualified contractor in the amount of $440,103.92 for a contract term of 3/4/25 to 3/3/28. Funding Source: RWRD Obligations Fund. Administering Department: Regional Wastewater Reclamation.
This project is expected to have multiple Guaranteed Maximum Price (GMP's) for construction services. The CMAR contractor's construction budget is not-to-exceed $12,000,000.00. Board of Supervisors to authorize the Procurement Director to execute all modifications, including one or more GMP packages, provided that the cumulative total of all GMP's and pre-construction services does not exceed $12,440,103.92 and the contract expiration date does not exceed 3/3/28, which allows for all contract close-out activities and final submittals.
|